Friday, October 22, 2010
Friday, October 15, 2010
Friday, October 8, 2010
The contractor has completed (paved) the first lift (of two) of asphalt on Bonnie Glen, Glenwood, and Harrison. Next week the contractor is scheduled to continue working on utility structure adjustments. The final lift of asphalt (hot-mix asphalt surface course) is scheduled to be paved in mid-October.
Friday, October 1, 2010
Friday, September 24, 2010
Friday, September 17, 2010
Friday, September 10, 2010
All sidewalk and curb & gutter has been completed on Harrison, Glenwood, Grove and Overlook. The contractor has completed the asphalt driveway repairs on Bonnie Glen, Meadowlark and the south part of Terrace. The contractor has started asphalt surface grinding this week and will continue grinding into next week.