Monday, December 6, 2010

Work is substantially complete with the exception of installation of detector loops, epoxy manhole lining and punch list work in various locations throughout the project.

Tuesday, November 30, 2010

Work is substantially complete with the exception of installation of detector loops, epoxy manhole lining, and punch list work in various locations throughout the project.

Monday, November 22, 2010

The contractor will continue with landscaping, manhole adjustments/repairs in the parkway, pavement markings, detector loops and punch list work in various locations throughout the project.

Wednesday, November 10, 2010

The contractor will continue with landscaping, manhole adjustments/repairs in the parkway, pavement markings, detector loops and punch list work in various locations throughout the project. The contractor is also scheduled to continue with replacing hot-mix asphalt driveway aprons on Crescent.

The contractor has completed the pavement patching in the Village Hall parking lot. The contractor still has work to complete to various utility structures in the Village Hall parking lot.

Friday, November 5, 2010

The contractor will continue with landscaping, manhole adjustments in the parkway, pavement markings, detector loops and punch list work in various locations throughout the project. The contractor is also scheduled to complete hot-mix asphalt patching in the Village Hall parking lot and hot-mix asphalt driveway aprons on Crescent late this week.

Monday, November 1, 2010

The contractor is substantially complete with the work with the exception of landscaping and manhole adjustments in the parkway in various locations.

Friday, October 22, 2010

The contractor has paved the final lift of hot-mix asphalt (surface course) on Glenwood, Wildwood, Bonnie Glen, Grove and Harrison. The contractor is scheduled to pave the final lift of hot-mix asphalt (surface course) on Franklin, Crescent, Brandess and Phillips late this week or early next week.