Friday, August 27, 2010

Concrete curb and gutter work has begun on Harrison, Grove, Overlook, Glenwood, and Dewes. Only spot repairs are being made in locations where the curb and gutter has deteriorated. Upon completion of the curb and gutter the contractor will prep for pavement resurfacing.


Curb and gutter work has not started and is not scheduled to start quite yet on the following streets: Phillips, Crescent, Franklin and Brandess.

Friday, August 20, 2010

The contractor is going to begin concrete curb and gutter removal next week.

Friday, August 13, 2010

Concrete curb and sidewalk repair work will begin the week of August 16 on the following streets:

Harrison, Glenwood, Grove, Overlook, Brandess, Phillips, Crescent, and Franklin. The resurfacing of these streets will follow soon after.

Saturday, August 7, 2010

New curb installation on Bonnie Glen was completed this week. The contractor plans to start the curb removal and replacement on the following streets next week: Glenwood, Grove, Harrison, Phillips, Brandess, Overlook, Crescent, Wildwood, Dewes, and Overlook. Each road is only getting spot repairs on the curb and gutter, meaning that only deteriorated sections will be removed and replaced.