Friday, October 22, 2010

The contractor has paved the final lift of hot-mix asphalt (surface course) on Glenwood, Wildwood, Bonnie Glen, Grove and Harrison. The contractor is scheduled to pave the final lift of hot-mix asphalt (surface course) on Franklin, Crescent, Brandess and Phillips late this week or early next week.

Friday, October 15, 2010

The contractor is scheduled to pave the final lift of hot-mix asphalt (surface course) next week on Glenwood, Wildwood, Bonnie Glen, Grove and Harrison. The contractor is scheduled to grind the existing pavement next week on Franklin, Crescent, Brandess and Phillips next week.

Friday, October 8, 2010

The contractor has completed (paved) the first lift (of two) of asphalt on Bonnie Glen, Glenwood, and Harrison. Next week the contractor is scheduled to continue working on utility structure adjustments. The final lift of asphalt (hot-mix asphalt surface course) is scheduled to be paved in mid-October.

Friday, October 1, 2010

The contractor has completed (paved) the first lift (of two) of asphalt on Bonnie Glen, Glenwood, and Harrison. Next week the contractor is scheduled to work on utility structure adjustments. The final lift of asphalt (hot-mix asphalt surface course) is scheduled to be paved in mid-October.