The strike was resolved this week and new contracts between the unions and contractors have been signed and are in effect. The contractor resumed work this week!

The contractor began storm and sanitary spot repairs and structure replacements on Bonnie Glen. This work will continue for the next few days, and then the contractor will move to Grove Street. Curb and gutter removal and replacement should commence next week. We have not yet received a schedule for this concrete work, but once I know it, I will update!